Not Defined
Develop a playbook for stormwater infrastructure retrofits to educate the public.
Green Stormwater Infrastructure, Water, & Energy

Owner

KB
Kevin Belanger

Update

Town infrastructure retrofits, Fire Station 1 Retrofit is at 100% design and the Stormwater Utility plans on construction beginning in Fall 2025. The Westwood Cemetery Rain Garden Retrofit is designed and will be funded with loop road construction. The Stormwater Utility continues to look for opportunities in the community for retrofit opportunities on Town owned Properties.   We also included in the Capital Projects funding to buy a parcel for future stormwater Retrofit in Downtown Carrboro.

Stormwater Utility staff have been assigned the deliverable of developing a Green Stormwater Infrastructure (GSI) Playbook to educate the public. The playbook will closely integrate with the Residential Assistance Program and work toward sharing the successes of GSI implementation within our community. Materials will be shared with Stormwater Advisory Commission as they are competed for feedback and adjustments.

Next Steps

The Fire Station retrofit has been bid and is expected to start construction this winter.   The Westwood cemetery rain garden design is at 80% and is anticipated to be bid in the spring.  The residential assistance program has a list of best practices that are being recommended to address stormwater issues on private property.   The Stormwater Utility will work to publish those practices so that they are readily accessible to the public, coordinating with the Stormwater Advisory Commission as the work takes place.

Phase

Analysis

Start Date

8/21/25

End Date

8/21/26

Gantt Chart

Name
Green Stormwater Infrastructure, Water, & Energy
Develop a playbook for stormwater infrastructure retrofits to educate the public.
2025
2026
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug