Delayed / On Hold
Council Priority #8: Eastrail
Council Priorities

City of Bellevue’s Council Priorities

Description

Council Priority #8: Work with King County and partner agencies to develop the Eastrail from Renton to Snohomish, including key projects and local connections in Bellevue. 

Period

Q2-26

Priority Status

Delayed / On Hold

Priority Status Legend

On Track |   Completed | Delayed/On hold | Not Started

Priority Icon

Staff Contact

Mike Ingram: [email protected]

Progress Updates

County work on the Eastrail is advancing, with elements in design, permitting and under construction. The Wilburton Trestle project is talking longer than initially planned, as the contractor has found more extensive deterioration in the historic wooden structure than was anticipated, requiring more extensive restoration work. City projects for Eastrail connections at Spring Blvd and at SE 32nd St/Mountains to Sound Greenway are also advancing, with some delay from the timeline initially anticipatedThe city project at 118th Ave SE/Mercer Slough is on track to be complete when the county opens the Eastrail segment between NE 4th St and 118th Ave SE (in mid/late 2027).  

Look Ahead

In fall 2026, construction is expected to start on the Eastrail to Spring Blvd Trail Link (city project)By late 2026 or early 2027 construction is expected to start on Eastrail development between NE 4th Street and 118th Ave SE/Mercer Slough as well as access improvements at 118th Ave SE (county project) 

Milestones

Delayed / On Hold
Signatures of 35 property owner needed.
Council Priorities
 | 
5/1/24 - 12/31/27
On Track
Historic Wilburton Trestle (King County Project)
Council Priorities
 | 
6/3/24 - 9/30/27
On Track
Construction underway to rehabilitate Wilburton Trestle
Council Priorities
 | 
6/3/24 - 9/30/27
Completed
Design underway
Council Priorities
 | 
3/3/25 - 12/29/28
Completed
Completed RFQ process, selected preferred consultant.
Council Priorities
 | 
Completed 3/31/26
Completed
Project kick off in January 2026
Council Priorities
 | 
Completed 1/30/26
On Track
Eastrail Crossing at SE 1st Street (King County Project)
Council Priorities
 | 
1/2/26 - 9/30/27
Not Started
Awarding construction contract.
Council Priorities
 | 
1/2/26 - 9/30/27
On Track
King County has submitted permit application to City
Council Priorities
 | 
1/2/26 - 9/30/27
Completed
Design and Permitting Complete
Council Priorities
 | 
Completed 4/13/26