In Progress
Ensure the City is green fleet ready for passenger vehicles & light-duty fleet
City of Maple Ridge Corporate Plan

Description

This key result involves the installation of Level-3 and Level-2 EV chargers at City Operations Centre to allow for the growth of the City's electric fleet. Over time the City is electrifying its fleet to achieve lower-carbon solutions for fleet operations and lower costs.

KR End Date

12/31/26

KR External Update

The City has been approved for Natural Resource Canada's Zero Emissions vehicle funding for this project.

For the City to be comprehensively green flleet ready for passenger and light duty vehicles, 2 separate phases of EV chargers must be installed.

Phase one of the project has been tendered and awarded.  Construction is expected to start in October and be completed by end of year. 

Planning for phase 2 of the project has started and work is underway.  However, given changes to the solar market dynamics, which has impacted original project estimates, the tender for phase 2 is expected to go public March 2026 with construction completed by end of 4th quarter 2026.

As such, the end date of the Key Result has been moved to December 2026 from December 2025. 

Initiatives

Complete
Secure Natural Resource Canada Zero Emissions Vehicle funding
City of Maple Ridge Corporate Plan | Completed 6/26/25
In Progress
Phase 1: Install 20 Level 2 EV fleet chargers
City of Maple Ridge Corporate Plan | 4/6/24 - 9/30/26
In Progress
Phase 2: Install 20 Level-2 and 2 Level-3 EV fleet EV chargers
City of Maple Ridge Corporate Plan | 6/29/24 - 9/30/26