Conduct a Recreation Facility Feasibility Study
City of Maple Ridge Corporate Plan

Description

Guided by the 2023 Parks, Recreation and Culture Master Plan that identified the need for new amenities like pools and ice rinks and Council's strategic plan, the recreation feasibility study commenced in 2024. The study includes extensive community engagement, analysis of current future demand for recreation facilities, site and technical assessments and a preliminary facility design concept to determine if Hammond Community Park is feasible to position a future aquatic facility at that site.

KR End Date

11/28/25

Complete?

Yes

Completed Date

12/31/25

KR Public Update

The Recreation Facility Feasibility Study has been completed. Initiated in January 2024, the study encompassed extensive community engagement, site and technical assessments, service demand analysis, building program development and preliminary concept design. The staff report was presented to Council on December 16, 2025. Council approved the recommendations to advance the planning to schematic design, prepare cost estimates and to develop a detailed funding strategy for all three recreation infrastructure projects:

  • Aquatics and Recreation Centre at Hammond Community Park
  • Arena Expansion at the Albion Fairgrounds
  • Multi-use Park Phase 1 at the Maple Ridge Golf Course

Staff are aiming to have the schematic design process and funding strategy development completed by summer 2026

Initiatives

Complete
Conduct an aquatics feasibility study to contemplate a second aquatics facility
City of Maple Ridge Corporate Plan
 | 
Completed 1/2/26