In Progress
Ensure the City is green fleet ready for passenger vehicles & light-duty fleet
City of Maple Ridge Corporate Plan

Description

This key result involves the installation of Level-3 and Level-2 EV chargers at City Operations Centre to allow for the growth of the City's electric fleet. Over time the City is electrifying its fleet to achieve lower-carbon solutions for fleet operations and lower costs.

KR End Date

12/31/26

Complete?

No

Completed Date

N/A

KR Public Update

To date, the City has secured a NRCan grant to support this project, and 20 Level-2 EV chargers have been installed.

Starting in August, an additional 20 Level-2 chargers and 2 Level-3 chargers are anticipated to begin installation.  The project is projected to be substantially complete by the end of February 2027.

Initiatives

Complete
Secure Natural Resource Canada Zero Emissions Vehicle funding
City of Maple Ridge Corporate Plan
 | 
Completed 6/26/25
Complete
Phase 1: Install 20 Level 2 EV fleet chargers
City of Maple Ridge Corporate Plan
 | 
Completed 7/9/26
In Progress
Phase 2: Install 20 Level-2 and 2 Level-3 EV fleet EV chargers
City of Maple Ridge Corporate Plan
 | 
6/29/24 - 2/26/27