In Progress
Ensure the City is green fleet ready for passenger vehicles & light-duty fleet
City of Maple Ridge Corporate Plan

Description

This key result involves the installation of Level-3 and Level-2 EV chargers at City Operations Centre to allow for the growth of the City's electric fleet. Over time the City is electrifying its fleet to achieve lower-carbon solutions for fleet operations and lower costs.

KR End Date

12/31/26

Complete?

No

Completed Date

N/A

KR Public Update

Phase 1 of the fleet charger project is under construction.  Approximately 50% complete. Weather has caused some delays in the pouring of the concrete foundations, but anticipated to be fully commissioned in early March.

Phase 2 project readying to get underway with tendering expected in February.  It is anticipated that the phase 2 project will be completed by Q3 of this year.

7 EV cars have been awarded to Ford via tender.  These vehicles are replacing hybrids at the end of lifecycle. 

Specifications are being prepared for the replacement of approximately 10 gas cargo vans. Scheduling coordination meetings with the user departments on requirements. 

 

Initiatives

Complete
Secure Natural Resource Canada Zero Emissions Vehicle funding
City of Maple Ridge Corporate Plan
 | 
Completed 6/26/25
In Progress
Phase 1: Install 20 Level 2 EV fleet chargers
City of Maple Ridge Corporate Plan
 | 
4/6/24 - 2/27/26
In Progress
Phase 2: Install 20 Level-2 and 2 Level-3 EV fleet EV chargers
City of Maple Ridge Corporate Plan
 | 
6/29/24 - 9/30/26