Hammond Road is Complete
Thorne Avenue 203 to 207 is proposed for design in 2024 (300k) and Construction in 2025 (3.3M)
117 Avenue 207 to Laity is complete
Laity 117 to H7 is complete
H7 Laity to 216 is complete
Gap H7 216 to 220 is delayed for coordination with upcoming BRT
H7 from 220 to 222 is complete
Gap A route through the Town Centre has yet to be established and prioritized in the capital plan. The Town Centre Road Network Strategy will confirm the route, a capital submission for design and construction is not in the 2024-2028 capital plan.
Lougheed 227 to Burnett is identified in the capital plan with 500k for design in 2026 and 4.35M for construction in 2028
Gap The last stretch from Burnett to 240 is not identified in the current 2024-28 capital plan.