Not Started
Phase 1: Install 20 Level 2 EV fleet chargers
City of Maple Ridge Corporate Plan

Planning Tier

Strategic Initiatives

Plans & Strategies

    Department

    Operations

    Accountable (Person ultimately accountable for the work, typically a Director)

    Supporting Dept(s)

      Informed (Anyone who needs to be kept updated about the progress)

      External Update

      • Dependent on the attainment of Natural Resources Canada Zero Emissions Vehicle Infrastructure Program funding.
      • Funding application was submitted in September 2024

      Start Date

      1/1/24

      End Date

      11/28/25

      Completed

      Not Completed

      Completion Date

      Not Completed