In Progress
Secure Natural Resource Canada Zero Emissions Vehicle funding
City of Maple Ridge Corporate Plan

Planning Tier

Strategic Initiatives

Plans & Strategies

    Department

    Strategic Development/Communications/Public Engagement

    Supporting Dept(s)

      External Update

      • Funding intake anticipated to open in July
      • Application development underway in tandem with Fleet EV Transition Plan
      • Application submission planned for August

      Start Date

      6/1/24

      End Date

      9/27/24