Needs Attention
Develop and implement green infrastructure design and maintenance specifications, guidelines, and performance standards
City of Maple Ridge Corporate Plan

Planning Tier

Strategic Initiatives

Plans & Strategies

    Department

    Engineering

    Accountable (Person ultimately accountable for the work, typically a Director)

    Supporting Dept(s)

    • Engineering
    • Planning
    • Strategic Development/Communications/Public Engagement

    Informed (Anyone who needs to be kept updated about the progress)

    External Update

    • The project has been put on hold due to vacancies in key positions related to the project. 
    • Project will resume in late 2024, pending the completion of recruitment processes.

    Start Date

    3/30/24

    End Date

    6/30/25

    Completed

    Not Completed

    Completion Date

    Not Completed