| | 19362 McNair Park RenovationsCapital Improvements and Innovation |
Period |
G.O. Bond Team |
A. Cantrero (Project Manager), L. Castellon (Project Coordinator), H. Danovich (Director)
Design Team |
Project Objectives |
Expand, renovate and equip this multi-functional facility to include lighted synthetic football/soccer field, running track, tennis court, basketball court, playground with water features to include splash pad, meeting rooms, concession and senior center.
Progress Update | |
installing plywood on the soffits and fascia all four sides of the building, continued with installing plywood on the ceiling on the south and east side of the building
The electrical contractor to start trenching and installing the 5-inch electrical conduits from the building to the back of the sidewalk
The framing contractor continued working inside the building, laying out and wall framing, crew completed the installation of the framing of the soffits and drip edge around the building
Crew continued working inside the building, laying out the floor, wall framing, door framing, installing door frames
The plumbing contractor continued installing water lines and drain pipes for the toilets and bathroom, installed main shut off valves on the east side of the building
The A/C contractor continued installation of the air ducts, insulation, vents, A/C refrigerant lines
The roofing contractor completed the work on the main roof installing insulations, concrete boards 4x8x ½ inch panels and covering with TPO Thermoplastic polyolefin single ply roofing membrane
Crew completed the foundation prep work and poured the footings
The sealing contractor onsite applying moisture water proofing sealant around the windows and doors openings ahead of the window installer
The FPL contractor has removed the pole, transformer and cables from the south side of the building
The painting contractor completed applying the undercoating and paint sealer on the underside of the roofing structure and panels on the east and north side of the building.
The electrical and plumbing contractors continued working inside the building, installing conduits and PVC roof drain pipes
The welding and fabrication contractor have completed roofing steel framework
Construction Progress Photos | |
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
DESIGN PHASE: March 2019 - May 2020
There are 5 phases before starting construction.
CONSTRUCTION PHASE: January 7, 2021 - Dec 31, 2021
Capital Project Images | |
Gantt Chart |