DESIGN PHASE: March 2019 - May 2020
There are 5 phases before starting construction.
- 1. Concept Phase
- 2. Schematic Phase
- 3. Design Development Phase
- 4. Construction Documents
- 5. Permitting for Construction
CONSTRUCTION PHASE: January 7, 2021 - Dec 31, 2021
Project Milestones, current and upcoming:
NTP Construction (Bldg Permit)-Bldg 09-Dec-20 , Start Foundations-Bldg 23-Mar-21
TOPOUT-Bldg 16-Jul-21 DRY-IN-Roof-Bldg 18-Aug-21
DRY-IN-Roofs/Windows-Bldg 20-Sep-21
Temp Power/Test-Bldg 04-Oct-21
Framing/RIs Complete-Bldg 11-Oct-21
Permanent Power-Bldg 14-Oct-21
HVAC Startup-Bldg 24-Oct-21
Finishes Complete-Bldg 09-Nov-21
Contract Duration to Substantial Completion 09-Dec-20 17-Nov-21
Substantial Completion-Actual-Bldg 30-Nov-21
Actual Duration to Estimated Substantial Completion 09-Dec-20 to 30-Nov-21