| | 19361 Terra Mar Drive Bridge RehabilitationCapital Improvements and Innovation |
Period |
G.O. Bond Team |
F. Thoney (Project Manager), L. Castellon (Project Coordinator), H. Danovich (Director)
Design Team |
Project Objectives |
This project consists of improvements to Terra Mar Drive Bridge, which was built in 1981. The plans were developed based on FDOT's Bridge Management System Report.
The project includes replacement recommendations for the deck, repairs to the superstructure, substructure, safety railings, utilities upgrades, and aesthetics enhancement.
Progress Update | |
Construction Progress Photos | |
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
SCHEDULE TASKS, IN PROGRESS AND UPCOMING:
Work Completed in SUMMER 2021:
•Whiting-Turner Subcontractor remobilized Monday (07/12/2021) to proceed
with work per RFI #4.1 Response & Permit Revision Approval.
•95% of all Vinyl Sheet Piles have been installed throughout the East & West
Seawall.
Work Projected in August/September 2021:
•Demolition of both East & West Seawall Cap to be completed.
•Bulkhead Rebar Installation to be completed for both East & West Seawall.
Capital Project Images | |
Gantt Chart |