Urban Forestry inspected exposed tree roots to determine potential impact to trees if City elected to widen roadway
More sidewalks poured, cut and backfilled along South side of 33rd yesterday. All sidewalks along South side of NE 33rd Street have been poured, cut and backfilled between Dixie Highway and NE 17th Avenue.
All utility access covers brought up to new sidewalk grade. Pouring new driveways for residents along South side of NE 33rd. Backfilling stripped driveways with compacted limerock along South side of street.
Once irrigation lines are installed along ends of stripped driveways, contractor will re-pave them and add swales.
All irrigation has been installed along both sides of NE 33rd between Dixie Highway and NE 16th Terrace
New ramps and ADA mats installed along both sides of NE 16th Terrace
Contractor directing traffic around equipment working in roadway
Bobcat backfilling completed irrigation lines along ends of driveways on South side of NE 33rd Street, as far East as NE 17th Avenue
After all new sidewalk and irrigation installations are completed, contractor will re-pave all selected driveways and add swales along South side of NE 33rd. Then, landscaping phase of work begins.