- Contractor, subcontractors and crews continued working onsite throughout July.
- Installed fascia boards on the west side roof of the building, and fascia boards on the high roof of the apparatus bay
- Crew continued to prep and paint the fascia boards and studs in the apparatus bay.
- Crew completed the roof framing on the generator pad enclosure, continued with the framework on the front porch and installing metal panels on the lower roof at the main entrance.
- Crew continued installing of the door frames on the 1st floor and 2nd floor of the building, prepped the door frames in the apparatus bay filling the sides with high strength concrete mixture prior to installation.
- The HVAC Contractor has installed two of the A/C units on the flat roof, vents and hoods, the a/c curb adapter has been installed on the flat roof, bolted down to the sub-roof floor.
- Crews continues working on the 1st and 2nd floor of the building with layouts of the floor, wall framing, HVAC air duct work and insulation, installing electrical metal conduits and pulling wires through the system to the outlets boxes, bathrooms and shower stalls, valves, water lines, floor drains and fire sprinkler system and wiring.
- The masonry contractor continued with the stucco work on the 1st floor of the building, apparatus bay storage area, the east staircase walls up to the 2nd floor and the vertical walls on the flat roof.
- Contractor core drilled the floor to run electrical main lines from the 1st floor up to the 2nd floor.
- The apparatus bay floor slab and drains system has been completed, the ceilings framework in the storage areas and entrance to the apparatus bay has been completed.
- The roofing subcontractor continued working on the roof crew continued installing 30# felt underlayment and tin caps, crew continued working on the lower roof and front porch at the main entrance of the building, constructing and installing joist, roof trusses and beams.
The contractor continued to maintained the construction site, removing trash debris and waste material, backfilled, rough grading and compacting around the building and entrances