| | 19374 Fire Station 52 and New Fuel DepotCapital Improvements and Innovation |
Period |
G.O. Bond Team |
J. Olsen (Project Manager), L. Castellon (Project Coordinator), H. Danovich (Director)
Design Team |
Project Objectives |
Replace the existing, outdated 41-year old fire station that services Palm Aire and Collier City with a new fire station to reduce response time and enhance fire and emergency services to the area which will include a new 2-story, multi-bay building.
Progress Update | |
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
DESIGN PHASE: Begins May 2019 Ends: March 2020
There are 5 phases before starting construction.
1. Concept Phase 4. Construction Documents
2. Schematic Phase 5. Construction Permitting
3. Design Development Phase
CONSTRUCTION PHASE: Anticipated Start date October 2021- End date January 2023
Capital Project Images | |
Gantt Chart |