| | 19371 Youth Sports ComplexCapital Improvements and Innovation |
Period |
G.O. Bond Team |
F. Thony (Project Manager), L. Castellon (Project Coordinator), H. Danovich (Director)
Design Team |
Project Objectives |
The Youth Sports Park project consists in transforming a 10+ acre site along NE 10th street in order to build out a new park facility to include multiple new lighted synthetic rectangular fields (soccer, football and lacrosse), new parking areas, landscaping , walking trails, decorative fencing and other new amenities such as bleachers, shades and/ or fitness stations.
Progress Update | |
Crew completed the parking lot subgrade on the north west side, grading rolling and compacting, passed inspection and density testing, and started backfilling with lime rock, grading, rolling and compacting
The landscape contractor moved three oak trees from the parking lot area, planted on the west side of the property
The shell subcontractor continued working on the building footers, laying out, installing forms, steel rebars and reinforcements to the footings
The electrical contractor continued installing conduits on the east side for the field lighting and camera system and passed inspection for the electrical conduits
The southwest parking lot subgrade inspection and density testing has passed and contractor continues working on the north west parking lot subgrade
Keith and associates have re-staked the new locations for the light pole due issues with the existing trees
Surveyors are staking out the 4th phase of the subgrade on the west side
The landscape crew has been watering trees and palms on a daily basis, and performed root pruning
FPL crew has completed removing the existing lighting poles from the site
The City crew installed the tap for the re-claimed water per contractor request
Construction Progress Photos | |
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
DESIGN PHASE: Begins May 2019 Ends: October 2020
There are 5 phases before starting construction.
1. Concept Phase 4. Construction Documents
2. Schematic Phase 5. Construction Permitting
3. Design Development Phase
CONSTRUCTION PHASE: Start date Phase 1- March 2021- End date December 2021
Capital Project Images | |
Gantt Chart |