A new park, including soccer/football field, concession, and restroom building to be located adjacent to Apollo Park at 1580 NW 3rd Ave.
Progress Update | |
This project is current undergoing additional budget review and value design engineering conducted by the team to bring the project within budget
The final drawings remain in progress
Coordination planning meetings are ongoing for this new park
Construction is estimated to begin in October 2021
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
DESIGN PHASE: Begins May 2019 Ends: February 2021
There are 5 phases before starting construction.
1. Concept Phase 4. Construction Documents
2. Schematic Phase 5. Construction Permitting
3. Design Development Phase
CONSTRUCTION PHASE: Anticipated Start date October 2021- End date Dec 2022