| | 19368 North Pompano Park ImprovementsCapital Improvements and Innovation |
Period |
G.O. Bond Team |
F. Thony (Project Manager), L. Castellon (Project Coordinator), H. Danovich (Director)
Design Team |
Project Objectives |
This project includes renovation of the existing park facility to include upgraded and new lighted synthetic rectangular fields (soccer, football and baseball), expanded parking areas, concessions, and new passive recreational areas, such as picnic lawn, new landscaping, access control, and pedestrian paths.
Progress Update | |
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
DESIGN PHASE: Begins May 2019 Ends: November 2020
There are 5 phases before starting construction.
1. Concept Phase 4. Construction Documents
2. Schematic Phase 5. Construction Permitting
3. Design Development Phase
CONSTRUCTION PHASE: Anticipated Start date March/April 2021- End date December 2021
Construction Progress Photos | |
Capital Project Images | |
Gantt Chart |