| | 19363 Amphitheatre Seating CoverageCapital Improvements and Innovation |
Period |
G.O. Bond Team |
A. Cantrero (Project Manager), L. Castellon (Project Coordinator), H. Danovich (Director)
Design Team |
Project Objectives |
Construct an open-air shade structure over the amphitheater seating area which was built in 1990.
Progress Update | |
Crew started assembling the 3rd section of the canopy fabric, cables and hardware, installed the baseplate for the vertical V beam on the east side of the bleachers, laid out the canopy fabric and the main assembly cables along the center staircase on the bleachers down to the stage.
Crew is installing brackets and bolts attaching the fabric to the main cables to be installed.
Contractor Big Span continued the installations of the canopy and permanent tie-down cables and brackets to the V-beams.
Crew formed and poured the concrete base around the baseplate for the radial trusses.
Crew prepped and poured the sidewalk slabs, east staircase ramp and landing on both east and west sides of the entryway to the Amphitheater.
Contractor received delivery of the baseplate for the number #8 vertical V beams to be installed on the east side of the amphitheater, first seven vertical V beams have been installed.
Contractor installed temporary cables to hold the Vertical beams in place and to hoist the lateral braces that will be connected to the radial trusses.
Big Span crew accidentally backed into one of the light poles east of the amphitheater and will restore the pole in the coming weeks.
Crew constructed and poured the east staircase ramp and head wall.
Crew completed welding steel plate on the west end of the vertical beam and will be prepping and painting the welding areas.
Construction Progress Photos | |
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
DESIGN/BUILD: December 2019 to October 2021
Construction is in progress with slight delays due to pile placement redesign, auger issues, unforeseen soil condition, and pile cap redesign
Upcoming tasks and milestones include:
Continue Parking Lot and Sidewalks Restoration
Courtyard Area and Restoration of Fencing
Complete Ventilation for Electrical Room
Replacement of Exit Signs
TCO/ Substantial Completion
PunchāOut
Final Completion