| | 19366 Kester Park Improvements ModernizationCapital Improvements and Innovation |
Period |
G.O. Bond Team |
A. Cantrero (Project Manager), L. Castellon (Project Coordinator), H. Danovich (Director)
Design Team |
Project Objectives |
Modernizing this 26-year old park by expanding the playground, open fields, ball fields, replacing dug outs and installation of perimeter fencing
Progress Update | |
Project is in final design. CMAR is working on possible GMP pricing.
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
Capital Project Images | |
Gantt Chart |