| | 19369 Senior Activity CenterCapital Improvements and Innovation |
Period |
G.O. Bond Team |
A. Cantero (Project Manager), L. Castellon (Project Coordinator), H. Danovich (Director)
Design Team |
Project Objectives |
To construct the first senior activity center in the City of Pompano Beach in response to the increasing demands of senior activity programs in the northwest sector of city. To promote and inspire activities that encourage involvement from the community in a supported environment.
Progress Update | |
Crew prepped and poured the building floor and continue installing concrete blocks erecting the vertical walls, constructing the horizontal beams, installing steel reinforcement and formwork.
The Plumbing contractor has completed the underground plumbing work, trenching and installing the PVC drains throughout the building sub floor.
The shell contractor completed the backfilling, hand grading and compacting the building floor sub-base, installation of the plastic sheeting and wire mesh for the floor foundation.
The electrical contractor continued installing electrical conduits along the sub-floor.
The drainage contractor continued working on the south side of the lot, excavating for the catch basin and perforated pipes.
Crew installed the stormwater drainage system on the north west side of the lot.
The landscape contractor removed all the tree stumps and vegetations off site.
The building pad has passed density test and inspection and the footings have been treated throughout with termite control pesticide.
The survey crew has staked out the parking lot, installing grade stakes and elevation markings for the subgrade.
The security camera system is still onsite, and gravel pad at both north and south entrances has been maintained by the general contractor.
Project Updates | |
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
PROJECT SCHEDULE MILESTONES - EXECUTIVE SUMMARY:
12-29-20 OWNER ISSUES NOTICE TO PROCEED
3-29-21 PERMITTING IN PLACE FOR PRACTICAL NOTICE TO PROCEED
1-14-22 SUBSTANTIAL COMPLETION/ TCO
3-11-22 OWNER PUNCHLIST & CORRECT & FINAL CO REQUIREMENTS
3-14-22 FINAL COMPLETION