| | 19369 Senior Activity CenterCapital Improvements and Innovation |
Period |
G.O. Bond Team |
A. Cantero (Project Manager), L. Castellon (Project Coordinator), H. Danovich (Director)
Design Team |
Project Objectives |
To construct the first senior activity center in the City of Pompano Beach in response to the increasing demands of senior activity programs in the northwest sector of city. To promote and inspire activities that encourage involvement from the community in a supported environment.
Progress Update | |
Construction Progress Photos | |
Approved Budget |
Construction Team |
Current Phase |
Percent Complete | |
Project Schedule |
PROJECT SCHEDULE MILESTONES - EXECUTIVE SUMMARY:
12-29-20 OWNER ISSUES NOTICE TO PROCEED
3-29-21 PERMITTING IN PLACE FOR PRACTICAL NOTICE TO PROCEED
1-14-22 SUBSTANTIAL COMPLETION/ TCO
3-11-22 OWNER PUNCHLIST & CORRECT & FINAL CO REQUIREMENTS
3-14-22 FINAL COMPLETION
Capital Project Images | |
Gantt Chart |