| Development Applications ProcessedPlanning |
Metric Definition |
The percent of site plan and subdivision development applications that are completely processed within 35 days (subject to council and/or staff approval).
Target Definition |
The "Target" is 100%; "Close To Target" is greater than 80%; anything less "Needs Improvement".
Organizational Effect |
The City prides itself on ensuring projects are handled in a professional, timely, consistent and accurate manner with the use of Plan Review Software and Qualified Staff to streamline the review process.
Target Data |
The Planning Department defines the targets and tracks the number of site and subdivision plans submitted on a monthly basis using Energov Plan Review Software.
Significance |
The Planning Department is dedicated to streamlining and consolidating the development review process to ensure projects succeed within the confines of adopted rules and regulations. Project review time is critical to economic growth within the City.
Chart |
Site Plan | Site Plan | Subdivision Plan | Subdivision Plan | |||
---|---|---|---|---|---|---|
Reporting Period | Submitted/Council Approval | Submitted/Staff Approval | Submitted/Council Approval | Submitted/ Staff Approval | Total Submitted/ Total Reviews | % on Target |
35 Days | 17 Days | 35 Days | 17 Days | |||
2020 | 19/19 | 14/14 | 6/6 | 7/7 | 46/46 | 100% |
2019 | 17/17 | 5 | 9/9 | 6/6 | 37/37 | 100% |
2018 | 25/25 | * | 6/6 | * | 30/30 | 100% |
2017 | 24/24 | * | 6/6 | * | 30/30 | 100% |
2016 | 25/25 | * | 5/5 | * | 30/30 | 100% |