Hutchinson and Associates have been contracted to develop engineered plans for the trail connection from Baker Road to Santavy. The project will include needed surveys, topo studies, needed CenterPoint permits and several pipeline permits. Parks & Recreation staff will request funds in the FY 2021 budget to complete Phase 7 of the Goose Creek Trail plan which will construct the trail from Baker Road to Cedar Bayou Lynchburg Road, including sidewalk connections and a connecting trail to Eddie Huron Park.
Goose Creek Trail Phase VII is funded by the MDD for the FY2021. Project is planned to start in early 2021.
Hutchinson and Associates will complete the design in November 2020. Construction for Phase VII to connect Baker Road north toward Cedar Bayou Lynchburg and connecting to the Eddie Huron Park Trail and access to the Country Club Cove subdivision with access to the Bush Road to San Jacinto sidewalk, is expected to be under construction in early 2021.