Develop and begin implementation of a plan to bring street signage into a uniform and standardized appearance. Increase replacement of faded or damaged signage.

1. Community Reputation & Image
Analysis

The Public Works Traffic Control Division developed a standard street sign layout. Conversion of signs to the new standard layout started with major intersections and in Council District 5, which is complete. Installing new signs across the City will take approximately three years. Currently, Decker is 90% complete, Market is 95% complete, W. Main is 90% complete, S. Main is 90% complete, and N. Alexander is 25% complete.  N. Main, Bayway and Hwy 146 are scheduled to start by the end of April.

Percent Complete
15 %
Attachments
  • New Baytown Street Sign
Start Date
10/1/17
End Date
9/30/18