On Target
Complete the Programmatic EIR and expand the permitting “tool kit” to facilitate broadband.
Board of Supervisors 2023

Description

In the County's efforts to expand rural broadband, we hear from internet service providers (ISP) that environmental permitting is a substantial challenge to complete projects in a timely and cost-efficient manner. As a result, the Broadband Work Group has led the effort to initiate a countywide environmental impact report (EIR) and a "tool kit" to help remove barriers to completing local "last-mile" projects. 

In 2021, the County hired Ascent Environmental, Inc. to complete the Draft Programmatic EIR. The EIR is expected to take approximately 8-10 months to complete and will involve multiple opportunities for public engagement. 

Progress Update

    1. The final Programmatic Environmental Impact Report (EIR) for the development of Broadband was completed in February 2023. The EIR will assist ISPs and developers with environmental analysis and legal compliance for the development of broadband throughout the county, thereby decreasing some associated costs of development.
    2. Staff is currently conducting comparative research across other jurisdictions on the development of a permitting “toolkit” to promote the expansion of broadband development. County staff have developed preliminary permitting flowcharts and decision trees that could be incorporated into the “toolkit”.

Next Steps

Conduct comparative research across other jurisdictions on the development of a permitting “toolkit” to promote the expansion of broadband development with aim to have a draft toolkit by early 2024.

Objectives

On Target
Broadband
Board of Supervisors 2023