On Target

Complete the Programmatic EIR and expand the permitting “tool kit” to facilitate broadband.

Board of Supervisors 2022

Description

In the County's efforts to expand rural broadband, we hear from internet service providers (ISP) that environmental permitting is a substantial challenge to complete projects in a timely and cost-efficient manner. As a result, the Broadband Work Group has led the effort to initiate a countywide environmental impact report (EIR) and a "tool kit" to help remove barriers to completing local "last-mile" projects. 

In 2021, the County hired Ascent Environmental, Inc. to complete the Draft Programmatic EIR. The EIR is expected to take approximately 8-10 months to complete and will involve multiple opportunities for public engagement. 

Progress Update

Q4-22

In the last quarter of 2022, the administrative final environmental impact report (EIR) was provided to County staff in late December.

Next Steps

Q4-22

In the first quarter of 2023, we anticipate seeking approval for the final programmatic EIR at a board meeting in February.

Objectives

On Target
Broadband
Board of Supervisors 2022