| AC1-SB Reduce turnaround time for routine cases to 30 days and rush cases to a maximum of two weeks.Support Bureau |
Strategic Direction |
Responsible Party - Lead |
Division / Unit / Section |
Funding Status |
Accomplishments | |
"January 28, 2021 to February 24, 2021
20 total cases currently in queue
246 total cases completed and reported
• ---58 BAC cases completed and reported; 6 BAC backlogged*
• ---188 CS cases completed and reported; 3 CS backlogged*
10 Rush cases requested 10 Rush cases completed within 14 days
100% of rush cases completed <14 days
100% total cases completed <30 days
Average days to complete case: 3.8 days
*LCMS training scheduled for Feb 23-26, 2021 for all analysts. RUSH cases are completed as promptly as possible, all others are backlogged until after training. "
Estimated Date of Completion |
Start Date |
End Date |