South - Initiate a plan to consolidate South Patrol Operations into one newer facility.

Patrol Bureau
Strategic Direction
  • 4: Technology Development and Infrastructure Expansion
  • Responsible Party - Lead
  • Patrol Deputy Chief
  • Division / Unit / Section
  • South Division (J)
  • Funding Status
  • Asset Forfeiture (AF)
  • Accomplishments

    This project was approved as part of the 2018 Bond Program. The City purchased the land in November 2018 and the design process began in 2019. The schematic design plans should be completed in November.

    Estimated Date of Completion
  • FY21
  • Start Date
    10/1/16
    End Date
    9/30/21